Working 21 hours a day to complete last basement project at Imam Hussain Shrine

Holy Shrine Projects

2020-02-12

586 Views

It is the third stage of constructing Bab Elqibleh basement at the Imam Hussain Shrine. This project is being implemented by the Department of Strategic Projects of the Imam Hussain Shrine.

Project’s director Engr. Selam Saadoon said, “The Engineering and technical personnel at the Imam Hussain Shrine have begun implementing the third stage of Bab Elqibleh basement project,” noting that 20% of the whole project has so far been completed.

Saadoon added that work is still underway, and the project encompasses 1,800m2.

“The next stage will be connecting all the basements in order to make more room for pilgrims,” indicated Sasdoon.

 

By: Hussain Hamid Elmoossewi

 

Recently Added

Most Popular

الزيارة الافتراضية

Other Topics of Interest